PLANNED MAINTENANCE - UPS SYSTEMS - TURING HOUSE 17TH,18TH AUGUST

Resolved At August 18, 2016 09:45

All,

The work to replace the batteries and near end of life parts in the UPS systems in Turing house has begun.

UPS1 - NOT AT RISK. UPS2 - NOT AT RISK. UPS3 - NOT AT RISK. UPS4 - NOT AT RISK - NOT SCHEDULED FOR ANY WORK EITHER DAY. UPS5 - NOT AT RISK - NOT SCHEDULED FOR ANY WORK EITHER DAY.

We do not expect any interruption to services as a consequence of any of this work, however if you have any questions or concerns please contact us ASAP.

Update 12:02 - The work on the UPS batteries for UPS1 has been completed and we are moving onto UPS2.

Update 12:38 - Engineers are currently taking a lunch break and all systems are up and NOT AT RISK.

Update 13:38 - Engineers have commenced work. UPS2 should be considered at risk until further notice.

Update 15:09 - The work on the UPS batteries for UPS2 has been completed and we are moving onto UPS3.

Update 15:47 - Work has been completed for the day. All systems are stable and optimal.

Work will continue in the morning and i'll keep a post updated here with progress.