Reynolds House - Mains ACB investigation

Resolved At February 24, 2017 08:59

Monday

We will shortly be completing work to switch the mains supply from switchboard 2.0 to switchboard 5.0. We do not expect any interruptions to service, however the site should be considered at risk until the next update.

Switching has been completed and Reynolds House is now supplied by the wrap around transformer and Switchboard 5.0. The next switching operation will be completed on Friday in order to return supplies to Switchboard 2.0 and the main transformer.

Friday - Following a successful maintenance